CES provided drainage, lighting, signing, and pav
ement
marking design for a northbound to eastbound connection between the
Turnpike Mainline and SR 408 in Orange County, Florida. The project
also included the widening of approximately one-half mile of the
Turnpike Mainline from four lanes to eight lanes and lighting design
along SR 408 between Clark Road/SR 50 connection and the Turnpike.
The drainage design included the design included the design of two
new retention ponds and seven roadside retention swales.